New Kusile unit powers up, 8 months ahead of schedule

For the first time on Sunday Kusile Unit 3 produced power, according to an internal memo to Eskom staff.

According to the note from Eskom's chief operating officer Jan Oberholzer, sent out to staff on Monday, the synchronisation of the unit happened eight months ahead of the scheduled December 2019. This is the third out of six Kusile units which have been synchronised to the national grid.

"The first synchronisation of Unit 3 marks a key milestone towards the full commercial operation of the unit.

"The next step will be the testing and optimisation of the unit which will result in it generating full power of 800MW of electricity, to be fed into the national grid for the country's consumption," Oberholzer said.

The unit is expected to be commercially operational, six months after the first synchronisation - or November 2019.

The first Kusile unit went live in August 2017. Each of the six units will produce 800MW of electricity, Fin24 previously reported.

At a previous briefing earlier in April on the status of the electricity system, Eskom board chair person Jabu Mabuza said that the construction of Kusile and Medupi Power stations would not be halted. The construction of both plants costs R36bn (R18bn each).

Mabuza explained that the benefit of concluding construction would outweigh the cost of stopping the projects.

Construction started as far back as 2007.

According to a report from the Sunday Times, the Special Investigating Unit is probing an alleged theft of R139bn from Eskom related to the construction of Medupi and Kusile power stations.


We live in a world where facts and fiction get blurred
Who we choose to trust can have a profound impact on our lives. Join thousands of devoted South Africans who look to News24 to bring them news they can trust every day. As we celebrate 25 years, become a News24 subscriber as we strive to keep you informed, inspired and empowered.
Join News24 today
heading
description
username
Show Comments ()
Rand - Dollar
19.21
-0.5%
Rand - Pound
23.95
-0.7%
Rand - Euro
20.56
-0.5%
Rand - Aus dollar
12.48
-0.7%
Rand - Yen
0.12
-0.2%
Platinum
912.40
-0.8%
Palladium
1,005.00
-2.1%
Gold
2,314.58
-0.3%
Silver
27.17
-0.5%
Brent Crude
88.42
+1.6%
Top 40
68,574
+0.8%
All Share
74,514
+0.7%
Resource 10
60,444
+1.4%
Industrial 25
104,013
+1.2%
Financial 15
15,837
-0.4%
All JSE data delayed by at least 15 minutes Iress logo
Company Snapshot
Editorial feedback and complaints

Contact the public editor with feedback for our journalists, complaints, queries or suggestions about articles on News24.

LEARN MORE
Government tenders

Find public sector tender opportunities in South Africa here.

Government tenders
This portal provides access to information on all tenders made by all public sector organisations in all spheres of government.
Browse tenders