Eskom wants to pollute more at Kusile to ease load shedding

accreditation
0:00
play article
Subscribers can listen to this article
Problems at Kusile power station contributed significantly to load shedding.
Problems at Kusile power station contributed significantly to load shedding.
Getty Images
  • Eskom has asked the environmental affairs department to allow it to bypass the flue-gas desulphurisation (FGD) units at the Kusile power station, which removes toxic sulphur dioxide.
  • Bypassing the FGD at three units at the station could return the units to operation a year earlier. 
  • This would then allow it to restore 2 100MW of generating capacity to the grid quicker in the midst of the country's load shedding disaster. 
  • For climate change news and analysis, go to News24 Climate Future.


Eskom, already named as the world’s biggest sulphur dioxide emitter, is seeking approval to release more of the pollutant linked to ailments ranging from asthma to heart attacks.

The move is part of an attempt by the company to reduce the level of temporary blackouts the nation is facing as a result of its inability to meet demand.

Eskom has asked South Africa’s environmental affairs department to allow it to bypass the flue-gas desulphurisation (FGD) unit, which removes the toxic gas (known by its chemical symbol SO2) from emissions at three of the six units at Kusile, the biggest coal-fired power plant in the world outside of Asia. 

By doing so, Eskom could return the units to operation a year earlier than if it first connected them to the FGD by building temporary structures while repairs continue to a duct that collapsed in October 2022. 

That, in turn, would allow the state-owned utility to restore 2 100MW of generating capacity to the grid at a time South Africa is suffering from a crippling energy shortage.   

Rotational blackouts occurred on more than 200 days in 2022 as Eskom’s plants repeatedly broke down, and varying levels of outages have been imposed every day so far in 2023. President Cyril Ramaphosa last week declared a state of disaster to enable the government to accelerate its response to the energy crisis.  

"The temporary stack solution will bypass the FGD and there will be an increase in the total mass of SO2 emissions from the stacks compared to the case where FGD was operating," Eskom said in a response to queries. "The environmental impact of these increased emissions is yet to be determined."

Kusile, one of Eskom’s two newest plants, is the only coal-fired one out of the 14 it operates to use the technology, which costs billions of dollars to install.

By temporarily bypassing the pollution abatement unit, Eskom will increase emissions of SO2 eightfold, to 80 000 tonnes at Kusile alone, said Lauri Myllivirta, lead analyst at the Centre for Research on Energy and Clean Air. Finland-based CREA said in a 2021 study that Eskom was the world’s biggest emitter of SO2.

"The pollutant is responsible for the brunt of the public health impacts caused by the company’s emissions," Myllivirta said in response to a query. If Eskom’s request is granted, it "would further add to the toll on public health associated with Eskom’s coal power emissions, which already stands at over 2 000 deaths a year," she said. 

Eskom disputes that figure, which has been cited in at least two studies, saying 320 deaths a year can be attributed to its emissions. 

The utility supplies almost all of South Africa’s electricity, with more than 80% of national supply coming from coal-fired plants. In addition to SO2, the company produces about 40% of the greenhouse gas emissions in South Africa, which is the world’s 13th biggest source of the climate-warming emissions.

*Editors note: This story has been corrected to reflect that the duct collapsed in October 2022 and not March 2022. 

We live in a world where facts and fiction get blurred
Who we choose to trust can have a profound impact on our lives. Join thousands of devoted South Africans who look to News24 to bring them news they can trust every day. As we celebrate 25 years, become a News24 subscriber as we strive to keep you informed, inspired and empowered.
Join News24 today
heading
description
username
Show Comments ()
Rand - Dollar
18.51
+0.3%
Rand - Pound
23.23
-0.0%
Rand - Euro
19.94
-0.1%
Rand - Aus dollar
12.22
+0.1%
Rand - Yen
0.12
+0.1%
Platinum
966.10
-0.0%
Palladium
950.00
-0.1%
Gold
0.00
0.0%
Silver
0.00
0.0%
Brent Crude
82.96
-0.9%
Top 40
70,300
+0.5%
All Share
76,428
+0.5%
Resource 10
60,246
-0.2%
Industrial 25
107,200
+1.3%
Financial 15
16,554
-0.2%
All JSE data delayed by at least 15 minutes Iress logo
Company Snapshot
Editorial feedback and complaints

Contact the public editor with feedback for our journalists, complaints, queries or suggestions about articles on News24.

LEARN MORE
Government tenders

Find public sector tender opportunities in South Africa here.

Government tenders
This portal provides access to information on all tenders made by all public sector organisations in all spheres of government.
Browse tenders